Lilybank Terrace - Fit Out Phase

Lilybank Fit Out

As the Shell and Core contract continues on site, our attention has, in recent weeks, turned to the production of fit out drawings for the Second Phase of the project. The main areas to tackle include the common entrance areas and corridors, internal stairs, doors, mezzanines and balustrading, internal features and window surrounds.

Our initial package of information will be discussed with the client next week and the specification will be determined.

Elsewhere on site, the second floor steelwork is now in place and the stone for the high level window surrounds has been ordered. We are now more than half way through the contract and the next phase of work should see the roof steelwork installed and the stone repairs concluded.