Work on the repair and shell works
contract at the Grade B Listed Townhouses at Lilybank Terrace got
underway in early January 2011 with Main Contractor Graham
Construction establishing a site presence and swiftly moving onto
ground enabling works with the first of the new steel frame set to
arrive before Easter.
This initial Phase of works will see
the new floor plates and steel frame formed and the building will
become wind and watertight during the 50 week contract.
The second phase fit out will follow
thereafter and is programmed to commence in the early part of
2012.