Lilybank Terrace

Lilybank terrace_blog image

Work on the repair and shell works contract at the Grade B Listed Townhouses at Lilybank Terrace got underway in early January 2011 with Main Contractor Graham Construction establishing a site presence and swiftly moving onto ground enabling works with the first of the new steel frame set to arrive before Easter.

This initial Phase of works will see the new floor plates and steel frame formed and the building will become wind and watertight during the 50 week contract.

The second phase fit out will follow thereafter and is programmed to commence in the early part of 2012.