As the Shell and Core contract continues on site, our attention
has, in recent weeks, turned to the production of fit out drawings
for the Second Phase of the project. The main areas to tackle
include the common entrance areas and corridors, internal stairs,
doors, mezzanines and balustrading, internal features and window
surrounds.
Our initial package of information will be discussed with the
client next week and the specification will be determined.
Elsewhere on site, the second floor steelwork is now in place
and the stone for the high level window surrounds has been ordered.
We are now more than half way through the contract and the next
phase of work should see the roof steelwork installed and the stone
repairs concluded.